It is planned to finish the installation works by the end of 2016:
- Finish transfer cabins, incl. sensors, cameras, vitrines, barriers, rolling doors;
- Basement works: cast concrete on lowest level, mount shifter guide rails, finish safety railings/fences, install safety zones, install crane for maintenance room, install cameras on TVs, install shifters;
- Establish IT network and servers;
Afterwards, over the next 6 months commissioning of the TVs, hoists, shifters and cabins will follow.
The system is expected to open to public in January 2018.